WeSolve’s Healthcare Team Delivers on Successful Community Hospital Relocation Project
Teamwork leads to a healthy outcome.
The Client
Community Hospital, Grand Junction, CO
- 140,000 square foot, state-of-the-art facility
- Nearly 300 physicians representing 55
- specialties
- Approximately 800 employees
Project Summary
Manage the relocation of hospital furnishings, equipment, supplies and patients to a new facility with no disruption to patient care. Consolidate and inventory remaining furniture and equipment. Work with numerous departments and individuals to help ensure relocated equipment is certified and approved for use.
The Challenge
Over its 70-year history, Community Hospital has outgrown two of its Grand Junction facilities and was now facing another relocation—this time to a new, four-story, 140,000-square-foot facility five miles from the current location. The move required the phased relocation of administrative offices, laboratories, clinical rooms and patient rooms with no disruption to service or healthcare.
The Solution
The WeSolve Healthcare Team, a specialty unit within the company, has successfully undertaken more than 480 healthcare facility projects. In fact, Community Hospital Vice President of Operations Debbie Riggle chose WeSolve as her project’s move manager after observing the team in action on another project.
The WeSolve team identified and addressed several logistical challenges during the planning process. There was limited access to the loading dock at the old facility, and after years of facility additions, parking lots were tight. This meant staging needed to be carefully choreographed to ensure efficient moving and minimal disruption.
The team met with each department to establish hour-by-hour timelines, educate the staff on the process, and to establish contingency plans.
The schedule was revised as needed, for example when the hospital’s Certificate of Occupancy was delayed well into the process.
The WeSolve team phased the project so that patient care capabilities were available at both sites as needed throughout the relocation process. Also, the team was on-site at the new facility six weeks before the actual move to receive, unpack, place, assemble and install the OFOI, OFVI and OFCI equipment over a two-week period.
We also worked with the environmental services, bio-med, infection control, respiratory therapy, information technology and facilities departments as well as the end users, to ensure relocated equipment was certified and approved for use. All remaining furniture and medical equipment was consolidated and inventoried immediately after the relocation.
The Result
During the relocation period, the hospital’s planning team met each day with all vendors to coordinate activity and share updates. At the final meeting, the WeSolve team was applauded by all for their exceptional service and attention to details, both large and small. More important to the WeSolve team of course was that the project was completed as planned so that patient care was uninterrupted.
Success That Moves Your Organization